Today I spent all day deburring tailcone skins and priming all the parts for the entire tailcone - 8 man hours
Saturday, April 29, 2023
Friday, April 28, 2023
Thursday, April 27, 2023
Tailcone part deburring
Spent some time this evening deburring tailcone parts. I am doing this section different by deburring everything up front and priming it before beginning construction. - 1.75 man hours.
Tuesday, April 25, 2023
Blue film removal on tailcone skins.....
Removed the blue film from all of the tailcone skins and other parts. - 2 man hours.
Sunday, April 23, 2023
Finished Stabilator!
Finished all the assembly of the stabilator! - 4.5 man hours.
Cleco'ed on the left skin.All done!
This thing is the most complex part in the kit so far. Must take your time and follow the directions. Part orientation is critical or it won't go together properly.
Another note. I see tons of blogs, videos and EAA builder sites where people are really skimping on the part edge prep and deburring. Whether you are priming or not, you should do a good job in this task otherwise you are inviting cracks to destroy your airplane in the future. Edges should be rounded, shear marks should be removed, all match drilled holes at a minimum should be deburred/chamfered. Personally I deburr/chamfer every hole regardless of how it came to be! I have no idea how some folks just take parts out of the crate and start riveting them together. Airplanes like that will almost certainly develop cracks in the future. Many times these cracks are in critical places where it is not so easy to find them.